- A project manager hired 16 men to complete a project in 40 days. However after 30 days he realized that only 4/9 th of the work is complete. How many more men does he need to hire to complete the project on time ?
A.30
B.32
C.44
D.40
E.None of theseAnswer – C.44
Explanation :
16*30 / 4/9 = M * 10/5/9
16*30*9/ 4 = M *10*9/5
1080 = 18M
M = 1080/18 = 60
Men required = 60 – 16 = 44 - 20 men can complete a piece of work in 15days and 12 women can complete the same piece of work in 24 days. What is the ratio of amount of work done by 30 men in oneday to the amount of work done by 16 women in 1 day ?
A.6:7
B.9:5
C.7:5
D.2:7
E.None of theseAnswer – B.9:5
Explanation :
M : W = 30/20*15 : 16/12*24
= 1/10 : 1/ 18 = 1/5:1/9
Ratio = 9:5 - X alone can do a piece of work in 5 days. Y can do the same piece of work in 4 days. X and Y are assigned to do the work for Rs.5000.They complete the work in 2 days with the help of Z. How much is to be paid to Z ?
A.Rs.750
B.Rs.620
C.Rs.700
D.Rs.500
E.None of theseAnswer – D.Rs.500
Explanation :
Z’s one day work = ½ – [ 1/5+1/4] = 10-4+5/20 = 1/20
Ratio = 1/5:1/4:1/20 = 4/20 : 5/20 : 1/20 = 4:5:1
Z = 5000*1/10 = 500 - 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?
A.36days
B.42days
C.30days
D.28days
E.None of theseAnswer – A.36days
Explanation :
9m+12w = 1/12
3m+4w = ?
3(3m+4w) = 1/12
3m+4w = 1/36 - P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?
A.7days
B.10days
C.5 days
D.12days
E.None of theseAnswer – D.12days
Explanation :
=1/6 + 1/12
=2+1/12 =3/12 = 1/4 - If X, Y and Z can complete a work in 6 days. If X can work twice faster than Y and thrice faster than Z, then the no of days Z alone can complete the work is
A.22 days
B.11 days
C.33days
D.30days
E.None of theseAnswer – C.33days
Explanation :
1/x+1/2x+1/3x = 1/6
6+3+2/6x = 6
11/6x = 6
X = 11
Z = 3x = 33 - If 20 men can do a piece of work in 42days working 8 hours per day then how many men are required to complete the work, working 5 hours per day in 33 days ?
A.39
B.47
C.32
D.41
E.None of theseAnswer – D.41
Explanation :
M = 20*42*8/5*33 = 40.72 = 41 - Three men, four women and six children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?
A.7
B.6
C.8
D.10
E.None of theseAnswer – A.7
Explanation :
2 men = 1 woman
1 man =1/2 woman
3 men =3/2 women
2 children = 1 man =1/2 woman
1 child =1/4 woman
6 children =6/4 =3/2 women
Now, three men, four women and six children
=3/2 + 4 +3/2 =3+8+3/2 = 14/2 = 7 women - If A can complete a work in 30 days, B can do the same work in 36 days, If after doing 5 days, leaves the work.Find in how many days B will do the remaining work ?
A.22days
B.28days
C.30days
D.36days
E.None of theseAnswer – C.30days
Explanation :
A = 1/30, B = 1/42
6 days work = 5*1/30 = 1/6
Remaining = 5/6
B = 5*36/6 = 30 - P is 20 % more efficient than Q, how much time will they working together take to complete a job which P alone could have done in 20 days ?
A.9 days
B.11 days
C.17days
D.22daya
E.None of theseAnswer – B.11 days
Explanation :
P : Q = 100 : 120
10/12 = 20/x
12/10 = x/20
X = 24
Q = 1/24 or 20*120/100 = 24
P+Q = 1/20 + 1/24
= 24+20/480 = 44/480 = 10.91 = 11 days
Note : Dear Friends if u know an alternate methods or shortcuts related to any chapter, you can share here.
AffairsCloud Recommends Oliveboard Mock Test
AffairsCloud Ebook - Support Us to Grow
Govt Jobs by Category
Bank Jobs Notification