Background of Project:
The project “Extension of Dry Dock-II” was sanctioned by the Ministry of Shipping under Central Sector Scheme with an outlay of Rs. 96.24 crores for extending the existing dock by 90 meters in length to accommodate more and bigger vessels. Its stipulated date of completion was 42 months during February 2016.
- This was not only to double the existing capacity of ship repair facilities at Port Blair but also to generate employment opportunities.
- The project work commenced at site on 07.03.2017 but due to some technical changes in the project, there was cost and time overrun. Now, the Ministry of Shipping has now approved the Revised Cost Estimate for an amount of Rs. 123.95 crore.